Bureau of Land Management Solar Energy Permitting and Program Resources
Quick Links
The BLM's updated Renewable Energy Rule went into effect on July 1, 2024. The information presented on this webpage is in the process of being updated.

BLM Evaluates Application

Procedures for Issuing Solar Energy ROW Grants Applicant-initiated action BLM-initiated action Major milestone BLM Issues ROW Grant BLM Evaluates Application Terms and Conditions for Grants Developer Submits Application Due diligence Assignments Issue notice to proceed Rent and applicable fees Performance and reclamation bond Finalize cost recovery Finalize plan of development Conduct NEPA evaluation Reject or prioritize application Variance concurrence (if applicable) Competitive bidding (if applicable) Initiate early tribal and interagency outreach Determine applicant technical/financial capabilities Preliminary meetings Initiate cost recovery Plan of development Application filing fee
Click on the steps in the diagram to learn more

When the BLM receives an application for a solar energy project on lands outside of designated leasing areas (DLAs), responsible staff start an adjudication process to determine whether to proceed with processing the application.

  • The BLM notifies the applicant that it has received the application and application fee. The BLM may assess additional fees during application processing if needed.
  • Most solar energy development applications for lands outside of DLAs will require preparation of an environmental impact statement (EIS) under the National Environmental Protection Act (NEPA) and more than 50 hours of federal work for processing (categorized as Processing Category 6 [43 CFR 2804.14]).

The BLM and applicant must enter into a written agreement that describes how the BLM will process the application, and discusses a project work plan, financial plan, and any existing agreements the applicant has with other Federal agencies for cost reimbursement associated with the application. In processing of the application, the BLM will:

  1. Determine the issues subject to analysis under NEPA.
  2. Prepare a preliminary work plan.
  3. Develop a preliminary financial plan, which estimates the reasonable costs of processing the application and monitoring the project.
  4. Discuss the following with the applicant: preliminary plans and data; availability of funds and personnel; applicant's options for the timing of processing and monitoring fee payments; and applicant financial information.
  5. Complete final scoping and develop final work and financial plans which reflect any work the applicant has agreed to do, including monitoring the project.
  • BLM may elect to prepare any environmental documents related to the application.
  • If BLM allows the applicant to prepare environmental documents and conduct needed studies, the work must follow BLM standards.
  • BLM will make the final determinations and conclusions arising from such work.