The Approved Record of Decision for Resource Management Plan Amendments for Utility-Scale Solar Energy Development was issued on December 20th, 2024 — details are available on the BLM's Utility-Scale Solar Energy Development PEIS/RMPA webpage. Relevant information on the 2024 Western Solar Plan and the BLM's Renewable Energy Rule issued in July 2024, is in the process of being updated on this website.
A plan of development (POD) is submitted when an application is submitted to the BLM. The POD schedule must meet the development schedule required by the BLM (43 CFR 2804.25(e.3)). This includes completing construction within the timeframes in the approved POD, but no later than 24 months after the start of construction, unless the project has been approved for staged development, or as otherwise authorized by the BLM.
The BLM will send a written response to an applicant when the application has been approved; this may include terms that prevent use of the right-of-way (ROW) until the POD has been approved and BLM has issued a Notice to Proceed. Construction, operation, maintenance, and termination of the facilities on the lands in the ROW must be done in a manner consistent with the approved POD.
The POD template (referenced at 43 CFR 2804.12 and available at https://www.blm.gov) includes a due diligence requirement that an applicant submit the POD within 90 days from application submission for applications for areas outside of DLAs. The POD template describes the following elements that must be included in the POD:
If an approved POD provides for staged development, unless otherwise approved by the BLM:
The grantee must maintain all onsite electrical generation equipment and facilities in accordance with the design standards in the approved POD.