Bureau of Land Management Solar Energy Permitting and Program Resources
Quick Links
The BLM's updated Renewable Energy Rule went into effect on July 1, 2024. The information presented on this webpage is in the process of being updated.

Select and Prepare Parcels

Major milestone BLM-initiated action Bidder/leasee-initiated action Due diligence Assignments Bonding Applicable fees Finalize plan of development Conduct NEPA evaluation (if not conducted prior to leasing) Cost recovery Rental payment Issue ROW lease Reject bids (if applicable) Bidding Variable offsets Notice of competitive offer Call for nominations(if applicable) Select and prepare parcels Initiate Competitive Process BLM ConductsCompetitive Offer BLM Selects Successful Bidder Terms and Conditions for Leases BLM Issues Notice to Proceed Procedures for Issuing Solar Energy ROW Leases Competitively
Click on the steps in the diagram to learn more

Parcels will be determined by the BLM but may consider configurations suggested through expressions of interest or nominations.

The BLM and other Federal agencies, as applicable, will conduct necessary studies and site evaluation work, including applicable environmental reviews and public meetings, before offering lands competitively.